Eastlake High School BotBall 2007 Week 1  February 19 - February 25 Week 2 February 26 - March 4 Week 3 March 5 - March 11 Week 4 March 12 - March 18 Week 5 March 19 - March 25 Week 6 March 26 - March 31
# Task/Event Sub Task/Event Pre-Requirements Person In Charge M T W TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W TH FR SA
1 Deadline #1 N/A Che                
2 Deadline #2 N/A Che                
3 Deadline #3 N/A Che                
4 Arena Construction N/A All              
   
5 Concepts    
5.1 Game Rules Workshop Jeff/Miguel              
5.2 Brainstorm Strategy Ideas Workshop All              
5.3 Brainstorm Robot Structure Workshop All              
5.4 Brainstorm Robot Programming Workshop All              
   
6 Final Decisions    
6.1 Final Strategy Ideas 5.2 All                
6.3 Final Robot Structure Ideas 5.3 All                
6.3 Final Robot Programming Ideas 5.4 All                
6.4 Recorded Rejected Concepts N/A All                
   
7 Construction    
7.1 Mechanical BOT 1  
7.1.1 Definition of Structure 6.2 All                
7.1.2 Definition of Mobility 6.2 All                
7.1.3 Make Model 7.1, 7.1.1, 7.1.2 Team Bot1                  
7.1.4 Test Model 7.1, 7.1.1, 7.1.2 Team Bot1                  
   
7.2   Mechanical BOT 2    
7.2.1 Definition of Structure 6.2 All                
7.2.2 Definition of Mobility 6.2 All                
7.2.3 Make Model 7.2, 7.2.1, 7.2.2 Team Bot2                  
7.2.4 Test Model 7.2, 7.2.1, 7.2.2 Team Bot2                  
   
7.3   Programming BOT 1    
7.3.1 Flow Chart 6.3 Edgar/Brock                
7.3.2 Create Code 6.3 Edgar/Brock                
7.3.3 Test and Modify 7.3, 7.3.1, 7.3.2 Edgar/Brock              
7.3.4 Final Code 7.3, 7.3.1, 7.3.2 Edgar/Brock                
   
7.4   Programming BOT 2    
7.4.1 Flow Chart 6.3 Edgar/Brock                
7.4.2 Create Code 6.3 Edgar/Brock                
7.4.3 Test and Modify 7.4, 7.4.1, 7.4.2 Edgar/Brock              
7.4.4 Final Code 7.4, 7.4.1, 7.4.2 Edgar/Brock                
   
8 Integration and Testing    
8.1 Integration of Robots 1 and 2 7 Edgar/Brock/Stan            
8.2 Test of Integration 7 Edgar/Brock/Stan                  
8.3 Modify any Bugs Discovered 8.1, 8.2 Edgar/Brock/Stan                  
   
9 Team Website Updates N/A Carlos/William                    
   
  Key: Fixed Milestone            
  Projected Finish Date            
  Mandatory Finish Date            
  Behind Schedule            
  Ahead of Schedule            
  On Time